Hengqin passageway on schedule with quality great

(cityofzhuhai.com)

Updated: 2020-09-16

High quality was maintained in constructing the Big Hengqin Mt Tunnel despite work falling behind two months, it was affirmed by experts at a Sept 14 conference concerning the safety and quality of Zhuhai engineering projects. 

The dual tunnels were broken through in December and March and will open to traffic by the end of this year as scheduled. To compensate for the delay caused by COVID-19, on Feb 16 the project was the first in Hengqin New Area to resume construction, having implemented automatic mechanized construction to increase efficiency. 

1.jpg

Tunnel entrance [Photo by Chen Xinnian / Guanhai App]

Chief engineer Su Guangming said that automatic machines save 5 million yuan ($737,000) and increase efficiency by more than 200 percent in the construction of every kilometer of tunnel compared with a manual labor force.

According to project manager Hao Deliang, the builders faced serious technical challenges. The 358-sq-m (428-sq-yd) excavated cross-section is equivalent to the surface of a basketball field, while the minimum net distance between Tunnels 1 and 2 was achieved at .54 m (1.77 ft).

In addition, the Big Hengqin Mt Tunnel had to pass over the Chimelong Tunnel and beneath both Zhuhai Airport Urban Rail Transit Phase II and Tiantai Mt Reservoir with gaps of 20.9 m (67 ft), 3.5 m (11.4 ft), and 144 m (471 ft) respectively.

China Railway 16th Bureau Group reports having introduced mature and rigorous rail system standards for tunnel construction, promoted the use of Building Information Modeling (BIM) technology, and improved concrete durability through cooperation with universities. To date, the project has obtained four national invention and five utility model patents, with no occurrence of accidents.

The 4.9-km (3-mile) passageway connects Hengqin and Central avenues in the north and a purposed South Qinhai Road in the south. It will be a key artery between Hengqin Island and the South Reclamation Area.


Related

2019-11-27

Big Hengqin Mt has one, shortly two, breakthroughs

The right half of the Number 2 tunnel under Big Hengqin Mt was broken through on Nov 25 while the excavation of the adjacent tunnel is well underway.

2020-03-03

Opening date unchanged for Big Hengqin Mt Tunnel

Construction of the Big Hengqin Mt Number 1 tunnel is back on a fast track with breakthrough expected by the end of this month.

2020-04-01

Big Hengqin passage being brought back on schedule

The second tunnel through Big Hengqin Mt was broken through on March 30 after 21 months of challenges which lately includes the COVID-19 outbreak.

Join in

64a9430a184ed00c2f309e22.jpg Moving 'Qingming Festival by the Riverside' on exhibition in Zhuhai

Piquing Interest

`.jpg Zhuhai islands aim high in tourism

Living Here

1.jpg Hong Kong-Macao residents guided into living in Zhuhai
Copyright © Zhuhai Municipal Government. All rights reserved. Presented by China Daily. 京ICP备13028878号-22